| Project
Experience:
Combustion Turbine Gas Supply
Dynegy
Riverside Gas Supply System Project
nine mile 20-inch
pipeline regulation station main line valves pipeline
appurtenances
design drafting mapping inspection
as-built documentation commissioning operations
East Kentucky Power Cooperative
Smith Plant Gas Supply System
seven mile 20inch
pipeline flow control metering & regulation facilities
pipeline appurtenances
survey right-of-way acquisition
design mapping permitting project & construction
management
Southern Illinois Power Cooperative
Marion Illinois Plant Gas Supply
System
six mile 12-inch
pipeline regulation & metering heater filter separators
survey design drafting mapping materials inspection
commissioning
Carolina Power & Light
Asheville Plant Gas Supply System
Project
four mile 12-inch
pipeline regulation heater filter separator
directional drills
feasibility study design drafting materials inspection
commissioning operator training
LG&E Capitol
Paddys Run Gas Supply System
Project
compressor station
regulation facilities filter/separation facilities
design drafting materials construction management
commissioning as-built documentation
Western Kentucky Energy
Reid/Green Plant Gas Supply Station
pipeline regulator
stations filter/separation in-plant piping
design drafting materials construction management &
inspection commissioning
North Carolina Natural Gas
CP&L Goldsboro Plant Gas Supply
System
regulation metering
filter/separation heaters slug catcher
design drafting material procurement commissioning
as-built documentation
Dynegy Power Corp.
Heard County Regulator Station
Project
regulator station to
delivery 3900 MCFH interconnect facilities
lump sum turnkey design materials fabrication
commissioning as-built documentation
|